Pipes, tanks and other equipment rust in the humid Southern air. Leaky roofs leave puddles on factory floors. Abandoned buildings are scattered across an 800-acre site contaminated with hundreds of tons of mercury.

If this were a factory making cars in Detroit or steel in Pennsylvania, it would have long ago been shuttered...

..At its root, it is bloated and mismanaged, say former Energy Department officials, outside experts and members of Congress.

The nation's nuclear weapons stockpile has shrunk by 85% since its Cold War peak half a century ago, but the Energy Department is spending nine times more on each weapon that remains. The nuclear arsenal will cost $8.3 billion this fiscal year, up 30% over the last decade.

The source of some of those costs: skyrocketing profits for contractors, increased security costs for vulnerable facilities and massive investments in projects that were later canceled or postponed.

"We are not getting enough for what we are spending, and we are spending more than what we need," said Roger Logan, a senior nuclear scientist who retired in 2007 from Lawrence Livermore National Laboratory. "The whole system has failed us."...

Now the Obama administration is moving forward with a plan to modernize the strategic weapons system over the next decade, an effort the Congressional Budget Office estimates will cost $355 billion. ...

"Simply stated, there is no plan for success with available resources," said Norman Augustine, a former Pentagon and defense industry official who is leading a review of the Energy Department's bomb program. ...

When the U.S. stockpile reached its peak in 1967 with 31,255 warheads and bombs, it cost $7 billion annually in today's dollars to build and maintain nuclear weapons.

In that year, the government had seven reactors humming to make plutonium; it built submarine reactors, refined large quantities of plutonium and uranium and manufactured new weapons. Almost once a week, it set off a bomb underground in Nevada.

Today, it does none of those things, but simply maintains the existing 4,804 weapons at $1.3 billion more than in 1967. ...

Don Cook, chief of the nation's nuclear weapons program for the Energy Department, argued that the size of the stockpile doesn't matter, because the facilities still have to have capability and special machines to repair even small numbers of weapons.

Profits paid to the contractors that run the system have tripled since 2006 to $312 million, The Times found.

The eight major nuclear weapon labs and production sites are run by a network of joint ventures and private companies, including the University of California, Bechtel Corp., Northrop Grumman Corp., Honeywell International Inc. and Lockheed Martin Corp.

Cook said the agency knew it would have to pay more to attract top-tier defense contractors. "Part of the deal was profit," he said.

As a result, profits paid to the new consortium hired to run the Los Alamos lab jumped tenfold to $59 million in 2013. At Lawrence Livermore National Laboratory, which is now run by the University of California and San Francisco-based Bechtel, among others, profits grew from $4 million to $41 million.

Full article is at 

http://www.latimes.com/nation/la-na-nukes-cost-20141109-story.html#page=1

Comments

Anonymous said…
Interesting, but a typical media hit piece. It's all gloom, too expensive, selected talking heads say this and that, etc. And, the way to fix problems is to spend money on them, but not spending enough money has been the cause of the problems noted in the article.

Popular posts from this blog

Plutonium Shots on NIF.

Tri-Valley Cares needs to be on this if they aren't already. We need to make sure that NNSA and LLNL does not make good on promises to pursue such stupid ideas as doing Plutonium experiments on NIF. The stupidity arises from the fact that a huge population is placed at risk in the short and long term. Why do this kind of experiment in a heavily populated area? Only a moron would push that kind of imbecile area. Do it somewhere else in the god forsaken hills of Los Alamos. Why should the communities in the Bay Area be subjected to such increased risk just because the lab's NIF has failed twice and is trying the Hail Mary pass of doing an SNM experiment just to justify their existence? Those Laser EoS techniques and the people analyzing the raw data are all just BAD anyways. You know what comes next after they do the experiment. They'll figure out that they need larger samples. More risk for the local population. Stop this imbecilic pursuit. They wan...

Trump is to gut the labs.

The budget has a 20% decrease to DOE office of science, 20% cut to NIH. NASA also gets a cut. This will  have a huge negative effect on the lab. Crazy, juts crazy. He also wants to cut NEA and PBS, this may not seem like  a big deal but they get very little money and do great things.

Rumor corner

LLNS may have excluded the wrong people in last VSSOP? The exclusions were based on outdated job categories and related skills. ULM are now thinking that in the future, job categories and functional areas will have to be re-defined. The next VSSOP/ISP will be based on the new categories and functional areas. The questions I have are: 1) Why didnt they think of that before the transition. It seems like their style is “change things as you go”. Planning is out the window! 2) Who will give input on the new changes? The next RIF apparently is going to be more lucrative than the VSSOP. Depending on the length of employment, a RIFed person, not only gets their 1 week pay per year of service but also from 30 to 120 days notice, essentially 30 to 120 days pay. Please feel free to comment on the rumors or add new ones you actually heard.