UPF's cost may soar above $11B
By Frank Munger
From the Knoxville News Sentinel
May 21, 2013
For
the past couple of years, the government has stood behind a cost range
of $4.2 billion to $6.5 billion for the Uranium Processing Facility, but
that range may not be able to contain the giant project's growing costs
as the schedule gets pushed into the future and funding gets stretched
out.
Todd Jacobson of Nuclear Weapons & Materials Monitor
this week reported that, based on a Government Accountability Office
briefing prepared for congressional committees, the cost of UPF could go
beyond the $6.5 billion estimated cap and perhaps go well beyond it.
According
to information in the GAO's 27-page briefing package, the "space/fit"
problem that forced the UPF team to re-do the building's design to
accommodate more equipment is a big part of the cost escalation. The GAO
cited NNSA documents that say the space problem will add $540 million
to the project's cost, delay the start of construction and delay the
start of facility operations by 13 months.
A bigger impact on the
overall cost, however, appears to be the possibility of the project
getting significantly lengthened due to funding constraints.
The
NNSA declined to comment on the GAO analysis or discuss any updates on
the estimated cost range for the Uranium Processing Facility.
The
GAO briefing notes that UPF cost estimates made in 2010-2011 timeframe
were based on annual appropriations not subject to budget constraints.
The NNSA, which placed the cost range at $4.2 billion to $6.5 billion in
that time frame, also planned on potentially changing the year-to-year
funding to meet the needs as the UPF moved from design to site
prepration to construction to operations.
In the same period, the
Army Corps of Engineers challenged the NNSA's estimated cost range for
UPF and came up with a range that went up to to $7.5 billion. The Corps
also did not foresee budgetary constraints, with the idea of the biggest
funding load coming with $900 per million per year for UPF in four
consecutive fiscal years.
Now, however, with schedules getting lengthened and some work getting deferred, the overall costs are reportedly climbing.
Under
less-optimum funding profiles, with limited appropriations (between
$200 million and $500 million annually), the overall cost of UPF could
go up to $11.6 billion and stretch the project out until FY 2035 -- the
GAO analysis of Corps of Engineers data suggests.
The GAO said the current cost range (up to $6.5 billion) for UPF does not include significant portions of the original scope.
The
briefing report said the NNSA in October 2012 updated its point
estimate -- the closest estimate to actual cost of UPF -- from $5.2
billion to $5.8 billion. The NNSA reportedly said it did not update the
cost range, which includes contingency for unknowns, at that time
because it's scheduled to get a complete review when the cost baseline
is established for the Critical Decision-2 process (which the contractor
plans to submit in September 2013).
The GAO concluded by saying it is "unclear" if the project's current cost range of $4.2B to $6.5B remains valid because:
-- NNSA's current "point estimate" is $6B as design cost for certain processing equipment has increased.
--
The space/fit issue ate up about 45 percent of the NNSA's contingency
for the project and the NNSA had not accounted for such a risk.
--
Several identified project risks, "including all risks related to
construction activities," are still out there and could require funding
to overcome in the future.
"It is possible that additional funds
will be needed to ensure there is sufficient contingency to complete the
UPF within a cost range that meets NNSA's 85 percent confidence level,"
the GAO briefing states. "As part of the CD-2 process, NNSA plans to
establish a firm cost baseline by June 2014."
Blog purpose
This BLOG is for LLNL present and past employees, friends of LLNL and anyone impacted by the privatization of the Lab to express their opinions and expose the waste, wrongdoing and any kind of injustice against employees and taxpayers by LLNS/DOE/NNSA.
The opinions stated are personal opinions. Therefore,
The BLOG author may or may not agree with them before making the decision to post them.
Comments not conforming to BLOG rules are deleted.
Blog author serves as a moderator.
For new topics or suggestions, email jlscoob5@gmail.com
Blog rules
- Stay on topic.
- No profanity, threatening language, pornography.
- NO NAME CALLING.
- No political debate.
- Posts and comments are posted several times a day.
Subscribe to:
Post Comments (Atom)
Posts you viewed tbe most last 30 days
-
No comment. https://www.msn.com/en-us/news/technology/goodbye-to-several-federal-jobs-these-are-the-jobs-elon-musk-has-said-will-be-cut/a...
-
If the Department of Energy (DOE) were eliminated, nuclear waste management in the U.S. would face significant challenges. The DOE is resp...
-
The end of LANL and LLNL? "After host Maria Bartiromo questioned whether the two plan to “close down entire agencies,” Ramaswamy said...
21 comments:
No big deal as long as you cut all funding to NIF, Z-Machine, Photon Science, Global Security, DOD and many other programs and concentrate on just building one and complete it on time.
CMMR on steroids?
Just rename it the Modern Pit Facility and all will be right in the universe.
And some people thought that the $4 billion figure for LANL's CMMR was too much?
Wow, Y-12 and the powerful Tennessee Congressional delegation sure did a number on NNSA and the rest of the Congress on this one. Guess another round of downsizing will have to take place at the NNSA labs to cover for the enormous increased funding expense of UPF.
And some people thought that the $4 billion figure for LANL's CMMR was too much?
May 25, 2013 at 10:34 PM
Old news was $4B, new news is closer to twice that number.
Old news was $4B, new news is closer to twice that number.
May 26, 2013 at 8:10 AM
After all, Lanl has to keep up with Y-12!
At least the CMRR-NF ceiling design was high enough.
Between corruption, incompetence and politics we've gutted our ability to even design and build a factory building.
Between corruption, incompetence and politics we've gutted our ability to even design and build a factory building.
May 27, 2013 at 3:46 PM
Who is "we"?? Are you part of the problem?
Y12 is more critical to the stockpile than CMRR. That's why they can screw up and still enjoy being rewarded for their incompetence. Now I'm not saying that CMRR is not important. CMRR should take much higher priority over NIF. In fact the two should never be compared in the same sentence. One is a critical multifaceted capability while the other is a sandbox for open-ended science.
Why is Y-12 critical to the US nuclear deterrent?
Why is Y-12 critical to the US nuclear deterrent?
May 29, 2013 at 4:50 PM
Uranium facility for nuclear weapon secondary stage refurbishment/repair/analysis/stewardship. No other reason.
Why build new secondary parts instead of new primary parts?
CMRR can do that. The big question is what NIF does, and more importantly, "what has NIF done for me lately?"
Why build new secondary parts instead of new primary parts?
May 29, 2013 at 7:49 PM
Try to learn a little bit about nuclear weapons before you make a bigger fool of yourself. There is lots of unclassified information out there that will explain the difference between the primary stage and the secondary stage of a nuclear weapon.
Haha reading this exchange gave me a chuckle.
Why was it more important to build a new uranium facility than a new plutonium facility?
Why was it more important to build a new uranium facility than a new plutonium facility?
May 31, 2013 at 4:56 AM
It isn't.
LANL can still build a limited number of pits per year without CMRR.
Y-12 can build a limited number of secondary parts without a new uranium facility.
UPF and CMMR are designed and intended to last 100 years - basically the last nuke production facilities we'll ever build. They will be used to keep the US stockpile around 1000 - 1500 warheads for the next 100 years.
Existing infrastructure can do this for say the next 20 or 30, but not 100 years. So you can stretch out construction of UPF over an additional 15 to 20 years, but as the articles on UPF cost point out, the longer you take to build the facility the more it cost.
Oh btw, why did I pick 100 years? There have been some interesting articles that speculate future technological advances will make strategic nuclear weapons impractical - pinpoint detection of subs at sea and orbital weapons to destroy them, kinetic kill vehicles for anti-ICBM reentry phase, etc. Replacing strategic nukes will be highly accurate hypersonic prompt delivery systems with conventional explosives. Just as 100 years ago, we would not have been able to envision nuclear weapons, today we cannot envision the actual strategic weapon systems that major countries will be using in 100 years.
This is cool!
Post a Comment